Iran Nuclear NewsIran denies delaying payment for reactor

Iran denies delaying payment for reactor

-

AP: The launch of a Russian-built nuclear power plant in Iran could be delayed because Iran has fallen behind in payments, Russian officials said Monday. Top Iranian officials swiftly denied that payments had been disrupted, in the latest dispute surrounding the deal at the heart of the two countries’ nuclear cooperation. Associated Press

By VLADIMIR ISACHENKOV

Associated Press Writer

MOSCOW (AP) – The launch of a Russian-built nuclear power plant in Iran could be delayed because Iran has fallen behind in payments, Russian officials said Monday. Top Iranian officials swiftly denied that payments had been disrupted, in the latest dispute surrounding the deal at the heart of the two countries’ nuclear cooperation.

Last year, Russia agreed to ship nuclear fuel to Bushehr – Iran’s first nuclear plant – by March 2007 and launch the facility in September, with electricity generation to start by November. Under a separate deal, Iran agreed to return to Russia all spent fuel from the plant in southern Iran for reprocessing – a move intended to assuage global concerns that the fuel could be diverted to make nuclear weapons.

Iran broke the schedule of payments this year under the $1 billion contract, said a Russian official, who asked not be named because he was not authorized to speak to the media. He said the Iranians blamed the delay on the need to switch payments from dollars to euros.

“The launch schedule definitely could be affected,” Sergei Novikov, a spokesman for Russia’s nuclear power agency, told The Associated Press.

But Mohammad Saeedi, the deputy head of the Atomic Energy Organization of Iran, denied that Iran had been late in making payments.

“Iran has had no delay whatsoever in making payments for the Bushehr nuclear power plant to the Russian … company,” Saeedi was quoted as saying by the news agency, IRNA.

Hashemi Rafsanjani, a former Iranian president who now heads a powerful clerical body called the Expediency Council, hinted that Russia was buckling under international pressure.

“We expect our friends (Russia) to prevent such attempts,” IRNA quoted Rafsanjani as saying.

The dispute came amid persistent diplomatic efforts to persuade Iran to halt uranium enrichment in order to allay international fears that it could be seeking nuclear weapons.

But while a delay in launching Bushehr is likely to anger Iran, there was no indication that Russia could be maneuvering to scrap the deal, which has provoked Western criticism. Russia emphasizes that Iran has the right to a peaceful nuclear energy program, and President Vladimir Putin and other officials have said repeatedly the Bushehr contract would be honored.

Putin’s increasingly defiant posture toward the United States would make it highly unlikely that the Kremlin would opt out of the agreement.

“Russia remains firmly committed to the Bushehr deal, and Putin’s recent statements make a change in attitude highly improbable,” said Yevgeny Volk, head of the Heritage Foundation’s Moscow office.

In December, Russia supported a U.N. Security Council resolution imposing limited sanctions against Iran over its refusal to stop uranium enrichment, but the support came only after a proposal imposing restrictions on the Bushehr plant was dropped.

The United States and some allies claim Iran’s nuclear program is aimed at developing nuclear weapons; Iran maintains it is only intended to generate electricity.

Iran has been eager to get the nuclear fuel from Russia, but Russian officials said it would only be delivered six months before the plant’s launch.

Prodded by the Iranians about the delivery, Igor Ivanov, secretary of Russia’s Security Council, said on a recent trip to Tehran that it would be delivered “when the need comes.”

Russian nuclear officials have complained before about payment delays for Bushehr.

Sergei Shmatko, the chief of the state Atomstroiexport company building the plant, said in December that Iran already had paid Russia $900 million for the plant’s construction. He added, however, that his company had provided a $140 million loan to Iran to finance construction because the Iranians had been slow about payments recently.

Latest news

30 Tir Uprising: The Historical Legacy of Iran’s Stand Against Dictatorship

The 30 Tir Uprising of July 21, 1952, stands as one of the defining moments in Iran’s modern history....

Iranian Regime Transfers Thousands of Centrifuges to Underground Mount Kolang Tunnel Complex

The Iranian regime has transferred thousands of uranium enrichment centrifuges to tunnels beneath "Mount Kolang," also known as "Pickaxe...

The Final Farewell of Two Political Prisoners Sentenced to Death in Iran

Abolfazl Sepahi and Alireza Sepahi, two prisoners sentenced to death in the case known as the "Alikhani Square" case...

Iran’s ‘No to Executions Tuesdays’ Campaign Marks130th Week

On Tuesday, July 21, the "No to Executions Tuesdays" campaign expanded to 59 prisons across Iran with the addition...

Eighth Day of Hunger Strike by 1,500 Prisoners in Ghezel Hesar Prison

The hunger strike and sit-in by about 1,500 prisoners sentenced to death in Unit 2 of Ghezel Hesar Prison...

Trump: The Final Phase of Destroying the Iranian Regime’s Missile and Nuclear Capabilities Has Begun

U.S. President Donald Trump announced that the United States' military operation against the Iranian regime has entered a broader...

Must read

Iran: 304 Executions in One Month, 1,735 In 2025 So Far

Executions by Iran's regime have reached an unprecedented level....

Iran warns of Western influence on Islamic press

Iran Focus: Tehran, Iran, Nov. 23 - Iran’s Minister...

You might also likeRELATED
Recommended to you